Nuclear Weapons: Action Needed to Address the W80-4 Warhead Program’s Schedule Constraints

15 min read
<div>The National Nuclear Security Administration (NNSA), a separately organized agency within the Department of Energy (DOE), has identified a range of risks facing the W80-4 nuclear warhead life extension program (LEP)—including risks related to developing new technologies and manufacturing processes as well as reestablishing dormant production capabilities. NNSA is managing these risks using a variety of processes and tools, such as a classified risk database. However, NNSA has introduced potential risk to the program by adopting a date (September 2025) for the delivery of the program's first production unit (FPU) that is more than 1 year earlier than the date projected by the program's own schedule risk analysis process (see figure). NNSA and Department of Defense (DOD) officials said that they adopted the September 2025 date partly because the National Defense Authorization Act for fiscal year 2015 specifies that NNSA must deliver the first warhead unit by the end of fiscal year 2025, as well as to free up resources for future LEPs. However, the statute allows DOE to obtain an extension, and, according to best practices identified in GAO's prior work, program schedules should avoid date constraints that do not reflect program realities. Adopting an FPU date more consistent with the date range identified as realistic in the W80-4 program's schedule risk analysis, or justifying an alternative date based on other factors, would allow NNSA to better inform decision makers and improve alignment between schedules for the W80-4 program and DOD's long-range standoff missile (LRSO) program. W80-4 Life Extension Program Phases and Milestone Dates NNSA substantially incorporated best practices in developing the preliminary lifecycle cost estimate for the W80-4 LEP, as reflected in the LEP's weapon design and cost report. GAO assessed the W80-4 program's cost estimate of $11.2 billion against the four characteristics of a high quality, reliable cost estimate: comprehensive, well-documented, accurate, and credible. To develop a comprehensive cost estimate, NNSA instituted processes to help ensure consistency across the program. The program also provided detailed documentation to substantiate its estimate and assumptions. To help ensure accuracy, the cost estimate drew on historic data from prior LEPs. Finally, to support a credible estimate, NNSA reconciled the program estimate with an independent cost estimate. GAO considers a cost estimate to be reliable if the overall assessment ratings for each of the four characteristics are substantially or fully met—as was the case with the W80-4 program's cost estimate in its weapon design and cost report, which substantially met each characteristic. To maintain and modernize the U.S. nuclear arsenal, NNSA and DOD conduct LEPs. In 2014, they began an LEP to produce a warhead, the W80-4, to be carried on the LRSO missile. In February 2019, NNSA adopted an FPU delivery date of fiscal year 2025 for the W80-4 LEP, at an estimated cost of about $11.2 billion over the life of the program. The explanatory statement accompanying the 2018 appropriation included a provision for GAO to review the W80-4 LEP. This report examines, among other objectives, (1) the risks NNSA has identified for the W80-4 LEP, and processes it has established to manage them, and (2) the extent to which NNSA's lifecycle cost estimate for the LEP aligned with best practices. GAO reviewed NNSA's risk management database and other program information; visited four NNSA sites; interviewed NNSA and DOD officials; and assessed the program's cost estimate using best practices established in prior GAO work. GAO is making two recommendations, including that NNSA adopt a W80-4 program FPU delivery date based on the program's schedule risk analysis, or document its justification for not doing so. NNSA generally disagreed with GAO's recommendations. GAO continues to believe that its recommendations are valid, as discussed in the report. For more information, contact Allison B. Bawden at (202) 512-3841 or bawdena@gao.gov.</div>

What GAO Found

The National Nuclear Security Administration (NNSA), a separately organized agency within the Department of Energy (DOE), has identified a range of risks facing the W80-4 nuclear warhead life extension program (LEP)—including risks related to developing new technologies and manufacturing processes as well as reestablishing dormant production capabilities. NNSA is managing these risks using a variety of processes and tools, such as a classified risk database. However, NNSA has introduced potential risk to the program by adopting a date (September 2025) for the delivery of the program’s first production unit (FPU) that is more than 1 year earlier than the date projected by the program’s own schedule risk analysis process (see figure). NNSA and Department of Defense (DOD) officials said that they adopted the September 2025 date partly because the National Defense Authorization Act for fiscal year 2015 specifies that NNSA must deliver the first warhead unit by the end of fiscal year 2025, as well as to free up resources for future LEPs. However, the statute allows DOE to obtain an extension, and, according to best practices identified in GAO’s prior work, program schedules should avoid date constraints that do not reflect program realities. Adopting an FPU date more consistent with the date range identified as realistic in the W80-4 program’s schedule risk analysis, or justifying an alternative date based on other factors, would allow NNSA to better inform decision makers and improve alignment between schedules for the W80-4 program and DOD’s long-range standoff missile (LRSO) program.

W80-4 Life Extension Program Phases and Milestone Dates

NNSA substantially incorporated best practices in developing the preliminary lifecycle cost estimate for the W80-4 LEP, as reflected in the LEP’s weapon design and cost report. GAO assessed the W80-4 program’s cost estimate of $11.2 billion against the four characteristics of a high quality, reliable cost estimate: comprehensive, well-documented, accurate, and credible. To develop a comprehensive cost estimate, NNSA instituted processes to help ensure consistency across the program. The program also provided detailed documentation to substantiate its estimate and assumptions. To help ensure accuracy, the cost estimate drew on historic data from prior LEPs. Finally, to support a credible estimate, NNSA reconciled the program estimate with an independent cost estimate. GAO considers a cost estimate to be reliable if the overall assessment ratings for each of the four characteristics are substantially or fully met—as was the case with the W80-4 program’s cost estimate in its weapon design and cost report, which substantially met each characteristic.

Why GAO Did This Study

To maintain and modernize the U.S. nuclear arsenal, NNSA and DOD conduct LEPs. In 2014, they began an LEP to produce a warhead, the W80-4, to be carried on the LRSO missile. In February 2019, NNSA adopted an FPU delivery date of fiscal year 2025 for the W80-4 LEP, at an estimated cost of about $11.2 billion over the life of the program.

The explanatory statement accompanying the 2018 appropriation included a provision for GAO to review the W80-4 LEP. This report examines, among other objectives, (1) the risks NNSA has identified for the W80-4 LEP, and processes it has established to manage them, and (2) the extent to which NNSA’s lifecycle cost estimate for the LEP aligned with best practices. GAO reviewed NNSA’s risk management database and other program information; visited four NNSA sites; interviewed NNSA and DOD officials; and assessed the program’s cost estimate using best practices established in prior GAO work.

What GAO Recommends

GAO is making two recommendations, including that NNSA adopt a W80-4 program FPU delivery date based on the program’s schedule risk analysis, or document its justification for not doing so. NNSA generally disagreed with GAO’s recommendations. GAO continues to believe that its recommendations are valid, as discussed in the report.

For more information, contact Allison B. Bawden at (202) 512-3841 or bawdena@gao.gov.

News Network

  • National Science Foundation: COVID-19 Affected Ongoing Construction of Major Facilities Projects
    In U.S GAO News
    What GAO Found Since GAO's April 2020 report on the status of the National Science Foundation's (NSF) major facilities projects, the Large Hadron Collider High Luminosity Upgrade program began construction, and it along with the four other major facilities projects in construction (see figure), have weathered schedule delays associated with the COVID-19 pandemic. To partially account for increased costs associated with the pandemic, such as the cost of paying project staff while work is paused, NSF has authorized $38.9 million in total project cost increases to the award recipients constructing three of the five projects: $18.9 million for the Daniel K. Inouye Solar Telescope, $10.0 million for the Vera C. Rubin Observatory, and $10.0 million for Regional Class Research Vessels. Because the pandemic is ongoing and its full effects are not yet known, NSF expects to make further adjustments to the cost and schedule of all five major projects in construction. Design work on an additional major facility project continued without significant interruption from the pandemic. Further, NSF made awards to begin the agency's first three mid-scale research infrastructure projects. National Science Foundation Major Facilities Projects in Construction NSF has fully implemented GAO's prior recommendation on information sharing among award recipients and has drafted guidance or taken other steps towards addressing GAO's three remaining recommendations. To enhance information sharing among award recipients, NSF added a section to its terms and conditions in its major facilities agreements that encourages awardees to share information among awardees and participate in a knowledge management program. Why GAO Did This Study NSF supports the design, construction, and operations of science and engineering research infrastructure such as telescopes and research vessels. These projects include major facilities that cost over $100 million to construct or acquire, and mid-scale research infrastructure projects. Over the past 5 fiscal years, NSF has received over $1 billion in appropriations for these projects. Prior GAO reports reviewed NSF's oversight of the projects, its cost estimating and schedule policies, and the project management expertise of its oversight workforce. Senate Report 115-275, Senate Report 114-239, and House Report 114-605 included provisions for GAO to review and report annually on projects funded from NSF's Major Research Equipment and Facilities Construction account. This report, the fourth, examines (1) the cost and schedule performance of NSF's ongoing major facilities and mid-scale research infrastructure projects and (2) the extent to which NSF has implemented prior GAO recommendations related to its management of major facilities. GAO reviewed NSF and award recipient documents for the projects. GAO examined policies and procedures to identify efforts to implement recommendations and interviewed NSF officials for clarifying information.
    [Read More…]
  • Japanese Shipping Company Fined $1.5 Million for Concealing Illegal Discharges of Oily Water
    In Crime News
    Misuga Kaiun Co. Ltd. (MISUGA), a Japanese-based company engaged in international shipping, was sentenced yesterday in federal court before U.S. District Court Judge Paul G. Byron in Orlando, Florida.
    [Read More…]
  • Six Charged in Connection with a $3 Million Paycheck Protection Program Fraud Scheme
    In Crime News
    Six individuals were charged in an indictment with fraudulently obtaining approximately $1.5 million in Paycheck Protection Program (PPP) loans on behalf of five businesses based in Georgia and South Carolina.
    [Read More…]
  • Puerto Rico: Perspectives on the Potential to Expand Air Cargo Operations
    In U.S GAO News
    Cargo was flown by air between more than 97 countries within the selected regions of Africa, Europe, Latin America, and the U.S. that may affect air cargo expansion in Puerto Rico. However, according to Department of Transportation (DOT) and European Union data, most international air cargo transportation was concentrated at a handful of countries and at airports in these regions. For example, four countries in Europe accounted for 72 percent of the U.S.-European Union air cargo transported, by weight. Likewise for airports, Miami International Airport accounted for 70 percent of air cargo transported between the U.S. and Latin America. Worldwide, cargo-only carriers transported on average 13.8 billion pounds of air cargo to and from the U.S. from 2016 through 2018. Of that cargo, two of the selected regions—Latin America and Europe—when combined accounted for 46 percent. Air Cargo Transported by Cargo-Only Airlines between the U.S. and Global Regions, Average Weight in Millions of Pounds, 2016 through 2018 Based on interviews with industry stakeholders and studies reviewed. GAO identified four factors that are generally associated with an airport's ability to attract air cargo traffic: (1) an airport's geographical location; (2) its proximity to transportation networks; (3) its supporting airport infrastructure and resources; and (4) the governmental and regulatory environments. For example, an airport located near businesses that generate large volumes of both inbound and outbound cargo that could be transported by air may be an important geographic factor for air carriers. Puerto Rican government and industry stakeholders GAO spoke with said that increased air cargo would benefit its airports and lead to positive effects on the Puerto Rican economy. For example, officials noted that expansion of air cargo operations could increase the use of underutilized airports and create opportunities for existing industry—such as the pharmaceutical, medical device, and aerospace industries—and help develop new ones. Puerto Rican and industry stakeholders had varying perspectives on the potential for Puerto Rico's expanding its air cargo operations. For example, some stakeholders said Puerto Rico's geographic location may allow it to serve as a refueling and cargo distribution point, particularly for flights between Europe and Latin America, while others said the island may be too close to some Latin American destinations to serve that purpose. Whether and to what extent Puerto Rico can increase air cargo operations depends on how air carriers weigh the various factors discussed above. Puerto Rico's economy has been in decline for much of the last 15 years and was devastated by hurricanes in 2017. Puerto Rico has sought to increase air cargo and passenger traffic at its international airports as a means to bolster and diversify its economy. Specifically, Puerto Rico seeks to serve as a transshipment point for transferring cargo between air carriers flying from Europe to Latin America. Air cargo, whether carried in the holds of passenger aircraft or by cargo-only aircraft, is an important component of global trade. The FAA Reauthorization Act of 2018 includes a provision for GAO to study the international air cargo transportation services among the United States and the African, Latin American, and European regions and the potential expansion of air cargo operations in Puerto Rico. This report addresses (1) what is known about air cargo operations between these world regions; (2) factors affecting the development of air cargo markets; and (3) Puerto Rican officials' and selected industry stakeholders' views on the economic effect and potential of expanding air cargo operations in Puerto Rico. GAO analyzed DOT and European air cargo data for flights between the U.S. and the selected regions for 2016 through 2018 (the latest available data). GAO also interviewed officials from DOT, and stakeholders from Puerto Rico and the air-cargo industry, selected based on prior GAO work and stakeholder mission. For more information, contact Heather Krause at (202) 512-2834 or krauseh@gao.gov.
    [Read More…]
  • Attorney General Merrick B. Garland Announces Results of Monitor Review
    In Crime News
    Today, at the International Association of Chiefs of Police annual meeting, Attorney General Merrick B. Garland announced the results of Associate Attorney General Vanita Gupta’s review of the use of monitors in civil settlement agreements and consent decrees with state and local governmental entities. In a memo to the Attorney General, the Associate recommended 19 separate actions that the department should take to improve its use of monitors in these cases.
    [Read More…]
  • Sanctions Against Businesses Linked to Mexican Cartels
    In Crime Control and Security News
    Michael R. Pompeo, [Read More…]
  • Disaster Response: Agencies Should Assess Contracting Workforce Needs and Purchase Card Fraud Risk
    In U.S GAO News
    The efforts of selected agencies to plan for disaster contracting activities and assess contracting workforce needs varied. The U.S. Forest Service initiated efforts to address its disaster response contracting workforce needs while three agencies—the U.S. Army Corps of Engineers (USACE), the U.S. Coast Guard, and Department of the Interior (DOI)—partially addressed these needs. The Environmental Protection Agency indicated it did not have concerns fulfilling its disaster contracting responsibilities. Specifically, GAO found the following: USACE assigned clear roles and responsibilities for disaster response contracting activities, but has not formally assessed its contracting workforce to determine if it can fulfill these roles. The Coast Guard has a process to assess its workforce needs, but it does not account for contracting for disaster response activities. DOI is developing a strategic acquisition plan and additional guidance for its bureaus on how to structure their contracting functions, but currently does not account for disaster contracting responsibilities. Contracting officials at all three of these agencies identified challenges executing their regular responsibilities along with their disaster-related responsibilities during the 2017 and 2018 hurricane and wildfire seasons. For example, Coast Guard contracting officials stated they have fallen increasingly behind since 2017 and that future disaster response missions would not be sustainable with their current workforce. GAO's strategic workforce planning principles call for agencies to determine the critical skills and competencies needed to achieve future programmatic results. Without accounting for disaster response contracting activities in workforce planning, these agencies are missing opportunities to ensure their contracting workforces are equipped to respond to future disasters. The five agencies GAO reviewed from above, as well as the Federal Emergency Management Agency (FEMA), collectively spent more than $20 million for 2017 and 2018 disaster response activities using purchase cards. GAO found that two of these six agencies—Forest Service and EPA—have not completed fraud risk profiles for their purchase card programs that align with leading practices in GAO's Fraud Risk Framework. Additionally, five of the six agencies have not assessed or documented how their fraud risk for purchase card use might differ in a disaster response environment. DOI completed such an assessment during the course of our review. An Office of Management and Budget memorandum requires agencies to complete risk profiles for their purchase card programs that include fraud risk. GAO's Fraud Risk Framework states managers should assess fraud risk regularly and document those assessments in risk profiles. The framework also states that risk profiles may differ in the context of disaster response when managers may have a higher fraud risk tolerance since individuals in these environments have an urgent need for products and services. Without assessing fraud risk for purchase card programs or how risk may change in a disaster response environment, agencies may not design or implement effective internal controls, such as search criteria to identify fraudulent transactions. The 2017 and 2018 hurricanes and California wildfires affected millions of people and caused billions of dollars in damages. Extreme weather events are expected to become more frequent and intense due to climate change. Federal contracts for goods and services play a key role in disaster response and recovery, and government purchase cards can be used by agency staff to buy needed items. GAO was asked to review federal response and recovery efforts related to recent disasters. This report examines the extent to which selected agencies planned for their disaster response contracting activities, assessed their contracting workforce needs, and assessed the fraud risk related to their use of purchase cards for disaster response. GAO selected six agencies based on contract obligations for 2017 and 2018 disasters; analyzed federal procurement and agency data; reviewed agencies' policies on workforce planning, purchase card use, and fraud risk; and analyzed purchase card data. FEMA was not included in the examination of workforce planning due to prior GAO work. GAO is making 12 recommendations, including to three agencies to assess disaster response contracting needs in workforce planning, and to five agencies to assess fraud risk for purchase card use in support of disaster response. For more information, contact Marie A. Mak at (202) 512-4841 or makm@gao.gov.
    [Read More…]
  • Secretary Antony J. Blinken at a Youth Moderated Discussion on Democracy and Human Rights
    In Crime Control and Security News
    Antony J. Blinken, [Read More…]
  • Soldiers charged with alien smuggling
    In Justice News
    Two Fort Hood active [Read More…]
  • Six Defendants Charged in Scheme to Defraud Student Loan Programs of More Than $12 Million.
    In Crime News
    Six former administrators from the Columbus, Georgia, campus of the Apex School of Theology were charged in an indictment unsealed Monday for their alleged participation in a scheme to defraud student loan programs of more than $12,000,000.
    [Read More…]
  • Department of Justice Announces Investigation of the Louisville/Jefferson County Metro Government and Louisville Metro Police Department
    In Crime News
    Attorney General Merrick B. Garland announced today that the Department of Justice has opened a pattern or practice investigation into the Louisville/Jefferson County Metro Government (Louisville Metro) and the Louisville Metro Police Department (LMPD).
    [Read More…]
  • Airborne Electronic Attack: Achieving Mission Objectives Depends on Overcoming Acquisition Challenges
    In U.S GAO News
    What GAO Found The Department of Defense’s (DOD) evolving strategy for meeting airborne electronic attack requirements centers on acquiring a family of systems, including traditional fixed wing aircraft, low observable aircraft, unmanned aerial systems, and related mission systems and weapons. DOD analyses dating back a decade have identified capability gaps and provided a basis for service investments, but budget realities and lessons learned from operations in Iraq and Afghanistan have driven changes in strategic direction and program content. Most notably, DOD canceled some acquisitions, after which the services revised their operating concepts for airborne electronic attack. These decisions saved money, allowing DOD to fund other priorities, but reduced the planned level of synergy among systems during operations. As acquisition plans have evolved, capability limitations and sustainment challenges facing existing systems have grown, prompting the department to invest in system improvements to mitigate shortfalls. DOD is investing in new airborne electronic attack systems to address its growing mission demands and to counter anticipated future threats. However, progress acquiring these new capabilities has been impeded by developmental and production challenges that have slowed fielding of planned systems. Some programs, such as the Navy’s EA-18G Growler and the Air Force’s modernized EC-130H Compass Call, are in stable production and have completed significant amounts of testing. Other key programs, like the Navy’s Advanced Anti-Radiation Guided Missile, have required additional time and funding to address technical challenges, yet continue to face execution risks. In addition, certain systems in development may offer capabilities that overlap with one another—a situation brought on in part by DOD’s fragmented urgent operational needs processes. Although services have shared technical data among these programs, they continue to pursue unique systems intended to counter similar threats. As military operations in Iraq and Afghanistan decrease, opportunities exist to consolidate current acquisition programs across services. However, this consolidation may be hampered by DOD’s acknowledged leadership deficiencies within its electronic warfare enterprise, including the lack of a designated, joint entity to coordinate activities. Furthermore, current and planned acquisitions will not fully address materiel-related capability gaps identified by DOD—including some that date back 10 years. Acquisition program shortfalls will exacerbate these gaps. To supplement its acquisition of new systems, DOD is undertaking other efforts to bridge existing airborne electronic attack capability gaps. In the near term, services are evolving tactics, techniques, and procedures for existing systems to enable them to take on additional mission tasks. These activities maximize the utility of existing systems and better position operators to complete missions with equipment currently available. Longer-term solutions, however, depend on DOD successfully capitalizing on its investments in science and technology. DOD has recently taken actions that begin to address long-standing coordination shortfalls in this area, including designating electronic warfare as a priority investment area and creating a steering council to link capability gaps to research initiatives. These steps do not preclude services from funding their own research priorities ahead of departmentwide priorities. DOD’s planned implementation roadmap for electronic warfare offers an opportunity to assess how closely component research investments are aligned with the departmentwide priority. Why GAO Did This Study Airborne electronic attack involves the use of aircraft to neutralize, destroy, or suppress enemy air defense and communications systems. Proliferation of sophisticated air defenses and advanced commercial electronic devices has contributed to the accelerated appearance of new weapons designed to counter U.S. airborne electronic attack capabilities. GAO was asked to assess (1) the Department of Defense’s (DOD) strategy for acquiring airborne electronic attack capabilities, (2) progress made in developing and fielding systems to meet airborne electronic attack mission requirements, and (3) additional actions taken to address capability gaps. To do this, GAO analyzed documents related to mission requirements, acquisition and budget needs, development plans, and performance, and interviewed DOD officials.
    [Read More…]
  • Congratulatory Message on the 30th Anniversary of the Visegrád Group (V4)
    In Crime Control and Security News
    Ned Price, Department [Read More…]
  • Secretary Antony J. Blinken and Senegalese Foreign Minister Aïssata Tall Sall at a Joint Press Availability
    In Crime Control and Security News
    Antony J. Blinken, [Read More…]
  • Keynote Address of Deputy Attorney General Jeffrey A. Rosen on Combatting Fraud in the Age of COVID-19 at the BBB National Programs NAD 2020 Conference
    In Crime News
    Remarks As Prepared For [Read More…]
  • Get to Know Preclearance
    In Travel
    Information for [Read More…]
  • Deputy Secretary Sherman’s Participation in an Extraordinary Session of the Strategic Stability Dialogue with Russian Deputy Foreign Minister Sergey Ryabkov
    In Crime Control and Security News
    Office of the [Read More…]
  • Ohio Man Pleads Guilty to Paying Co-Conspirator to Illegally Dump Drums of Hazardous Waste
    In Crime News
    An Ohio man pleaded guilty in the Southern District of Ohio before U.S. District Judge Edmund A. Sargus Jr. to conspiring to illegally transport and dispose of hazardous waste at several area apartment complexes.
    [Read More…]
  • Conroe man charged with funneling money to India
    In Justice News
    A 48-year-old local man [Read More…]
  • Anti-Money Laundering: Opportunities Exist to Increase Law Enforcement Use of Bank Secrecy Act Reports, and Banks’ Costs to Comply with the Act Varied
    In U.S GAO News
    Many federal, state, and local law enforcement agencies use Bank Secrecy Act (BSA) reports for investigations. A GAO survey of six federal law enforcement agencies found that more than 72 percent of their personnel reported using BSA reports to investigate money laundering or other crimes, such as drug trafficking, fraud, and terrorism, from 2015 through 2018. According to the survey, investigators who used BSA reports reported they most frequently found information useful for identifying new subjects for investigation or expanding ongoing investigations (see figure). Estimated Frequency with Which Criminal Investigators Who Reported Using BSA Reports Almost Always, Frequently, or Occasionally Found Relevant Reports for Various Activities, 2015–2018 Notes: GAO conducted a generalizable survey of 5,257 personnel responsible for investigations, analysis, and prosecutions at the Drug Enforcement Administration, Federal Bureau of Investigation, Homeland Security Investigations, Internal Revenue Service-Criminal Investigation, Offices of U.S. Attorneys, and U.S. Secret Service. The margin of error for all estimates is 3 percentage points or less at the 95 percent confidence interval. As of December 2018, GAO found that the Financial Crimes Enforcement Network (FinCEN) granted the majority of federal and state law enforcement agencies and some local agencies direct access to its BSA database, allowing them to conduct searches to find relevant BSA reports. FinCEN data show that these agencies searched the BSA database for about 133,000 cases in 2018—a 31 percent increase from 2014. FinCEN created procedures to allow law enforcement agencies without direct access to request BSA database searches. But, GAO estimated that relatively few local law enforcement agencies requested such searches in 2018, even though many are responsible for investigating financial crimes. GAO found that agencies without direct access may not know about BSA reports or may face other hurdles that limit their use of BSA reports. One of FinCEN's goals is for law enforcement to use BSA reports to the greatest extent possible. However, FinCEN lacks written policies and procedures for assessing which agencies without direct access could benefit from greater use of BSA reports, reaching out to such agencies, and distributing educational materials about BSA reports. By developing such policies and procedures, FinCEN would help ensure law enforcement agencies are using BSA reports to the greatest extent possible to combat money laundering and other crimes. GAO reviewed a nongeneralizable sample of 11 banks that varied in terms of their total assets and other factors, and estimated that their total direct costs for complying with the BSA ranged from about $14,000 to about $21 million in 2018. Under the BSA, banks are required to establish BSA/anti-money laundering compliance programs, file various reports, and keep certain records of transactions. GAO found that total direct BSA compliance costs generally tended to be proportionally greater for smaller banks than for larger banks. For example, such costs comprised about 2 percent of the operating expenses for each of the three smallest banks in 2018 but less than 1 percent for each of the three largest banks in GAO's review (see figure). At the same time, costs can differ between similarly sized banks (e.g., large credit union A and B), because of differences in their compliance processes, customer bases, and other factors. In addition, requirements to verify a customer's identity and report suspicious and other activity generally were the most costly areas—accounting for 29 and 28 percent, respectively, of total compliance costs, on average, for the 11 selected banks. Estimated Total Direct Costs for Complying with the Bank Secrecy Act as a Percentage of Operating Expenses and Estimated Total Direct Compliance Costs for Selected Banks in 2018 Notes: Estimated total direct compliance costs are in parentheses for each bank. Very large banks had $50 billion or more in assets. Small community banks had total of assets of $250 million or less and met the Federal Deposit Insurance Corporation's community bank definition. Small credit unions had total assets of $50 million or less. Federal banking agencies routinely examine banks for BSA compliance. FinCEN data indicate that the agencies collectively cited about 23 percent of their supervised banks for BSA violations each year in their fiscal year 2015–2018 examinations. A small percentage of these violations involved weaknesses in a bank's BSA/anti-money laundering compliance program, which could require the agencies by statute to issue a formal enforcement action. Stakeholders had mixed views on industry proposals to increase the BSA's dollar thresholds for filing currency transaction reports (CTR) and suspicious activity reports (SAR). For example, banks must generally file a CTR when a customer deposits more than $10,000 in cash and a SAR if they identify a suspicious transaction involving $5,000 or more. If both thresholds were doubled, the changes would have resulted in banks filing 65 percent and 21 percent fewer CTRs and SARs, respectively, in 2018, according to FinCEN analysis. Law enforcement agencies told GAO that they generally are concerned that the reduction would provide them with less financial intelligence and, in turn, harm their investigations. In contrast, some industry associations told GAO that they support the changes to help reduce BSA compliance costs for banks. Money laundering and terrorist financing pose threats to national security and the U.S. financial system's integrity. The BSA requires financial institutions to file suspicious activity and other reports to help law enforcement investigate these and other crimes. FinCEN administers the BSA and maintains BSA reports in an electronic database that can be searched to identify relevant reports. Some banks cite the BSA as one of their most significant compliance costs and question whether BSA costs outweigh its benefits in light of limited public information about law enforcement's use of BSA reports. GAO was asked to review the BSA's implementation. This report examines (1) the extent to which law enforcement uses BSA reports and FinCEN facilitates their use, (2) selected banks' BSA compliance costs, (3) oversight of banks' BSA compliance, and (4) stakeholder views of proposed changes to the BSA. GAO surveyed personnel at six federal law enforcement agencies, collected data on BSA compliance costs from 11 banks, reviewed FinCEN data on banking agencies' BSA examinations, and interviewed law enforcement and industry stakeholders on the effects of proposed changes. GAO is recommending that FinCEN develop written policies and procedures to promote greater use of BSA reports by law enforcement agencies without direct database access. FinCEN concurred with GAO's recommendation. For more information, contact Michael Clements at (202) 512-8678 or clementsm@gao.gov.
    [Read More…]

Crime

Network News © 2005 Area.Control.Network™ All rights reserved.